[ SPECIAL SYSTEMS History ] While Mass. Electric is well known and respected for their electrical construction work, we have secured, protected and connected a long list of customers:
Walt Disney World Orlando, FL
Owner: Walt Disney World
General Contractor: Direct to owner
Completion Date: 1998
Furnished and installed Gates access systems, security cameras, cash movement tracking systems, fiber optic networks and a central monitoring system.
Hynes Convention Center Boston, MA
Owner: Massachusetts Convention Center Authority
General Contractor: MAC Systems
Completion Date: 2002
Furnished, installed and integrated with building systems, access control and CCTV systems.
EMC Franklin, MA & Hopkinton, MA
Owner: EMC Corporation
General Contractor: Macomber Construction
Completion Dates: Franklin, November 1998; Hopkinton - Phase 1A, January 2000; Hopkinton - Phase 1B, January 2001
Design-support and installation of voice and data networks in new manufacturing and office/research facilities. Hopkinton facility system includes Certified Category 6 and fiber to the desk.
PSInet Bedford, MA
Owner: PSInet
General Contractor: Clark Technologies
Completion Date: 2000
Renovation of existing building to a new 50,000 sq. ft. co-hosting telecommunications data center. The finished computer room area is 25,000 sq. ft.
Fidelity World Trade Center Boston, MA
Owner: Fidelity Investments
General Contractor: Payton Construction
Completion Date: June 2001
Year-long 5,000 drop recabling project at Fidelity’s World Trade Center location including installation of redundant fiber backbone to twelve communications rooms.
Raytheon Corp. Lexington, MA
Owner: Raytheon
General Contractor: Direct to Owner
Completion Date: On-going
Maintenance of 160 mile Rayfon fiber optic network since 1991.
State Street Bank Boston & Quincy, MA
Owner: SSB
General Contractor: Direct to Owner
Completion Date: On-going
15,000 users in several buildings, complete network plus maintenance.
John Joseph Moakley U.S. Courthouse Boston, MA
Owner: General Services Administrator
General Contractor: Lucent
Completion Date: 1998
Installation of a complete LAN for 2500 users in the new 10-story facility. Furnished and installed intrusion, video surveillance, panic alarms and metal detection systems.
Fidelity Investments Smithfield, RI
Owner: Fidelity
General Contractor: Gilbane
Completion Date: 1998
Installation of a complete LAN for 1700 users in the new four-story facility.
State Street Bank Westwood, MA
Owner: SSB
General Contractor: Direct to Owner
Completion Date: 1998
Installation of a complete LAN for 1600 users in the remodeled facility.
Fidelity Investments Merrimack, NH & Boston, MA
Owner: Fidelity
General Contractor: Macomber Const.
Completion Date: 1997
5,000 users in several buildings, complete network.
Boston University School of Management Boston, MA
Owner: BU
General Contractor: Morganti Construction
Completion Date: 1997
2,400 users on six floors, complete network.
Global Crossing Centers: Phase 1 Waltham, MA
Owner: Global Crossing
General Contractor: Richard White & Sons
Completion Date: 2001
Renovation of existing building to a new 175,000 sq. ft. co-hosting telecommunications data center. MEC’s Engineering Department provided design assistance on this fast-track project that will require 200 electricians to complete. The finished computer room area is 140,000 sq. ft. |
[ DID YOU KNOW? ]
MEC’s experience modification factor is 0.51 proactive continuous improvement programs. |
|